Give us a Call
Notification requirements and fees
Now that you’ve reviewed the asbestos requirements for renovation and demolition projects, and you’ve determined if your project qualifies as an owner-occupied, single-family residence or not, below are notification waiting periods and fees.
Owner-Occupied, Single-Family Residence
Asbestos removal to be done by the owner-occupant:
Notification Waiting Period: Not Required
Fee: $0
________
Asbestos removal to be done by an abatement contractor for
10 linear feet or more, and/or 48 square feet or more (per residence, per calendar year)
Notification Waiting Period: Prior notice required
Fee: $0
________
Any demolition work
Notification Waiting Period: 3 days
Fee: $30
All Other Projects
Less than 10 linear feet and/or less than 48 square feet of asbestos removal making total (per structure, per calendar year) less than 10 linear feet and/or less than 48 square feet
Notification Period: None
Fee: $0
________
Less than 10 linear feet and/or less than 48 square feet of asbestos removal, but total removal (per structure, per calendar year) more than 10 linear feet and/or more than 48 square feet
Notification Period: Prior Notice Required
Fee: $75
________
10-259 linear feet and/or 48-159 square feet
Notification Period: 3 day notice
Fee: $250A
A = Includes demolition fee (if applicable) provided the asbestos and demolition projects are submitted on one notification.
________
260-999 linear feet and/or 160-4,999 square feet
Notification Period: 10 day notice
Fee: $500A
A = Includes demolition fee (if applicable) provided the asbestos and demolition projects are submitted on one notification.
________
1,000 or more linear feet and/or 5,000 or more square feet
Notification Period: 10 day notice
Fee: $1,250AB
A = Includes demolition fee (if applicable) provided the asbestos and demolition projects are submitted on one notification.
B = An added fee of $250 shall be paid for each increment of up to 1,000 linear feet when removing 2,000 or more linear feet.
B = An added fee of $250 shall be paid for each increment of up to 10,000 square feet when removing 10,000 or more square feet.
________
Any demolition work
Notification Period: 10 day notice
Fee: $250
Additional Categories
Amendment of Notification
Notification Period: Prior notice required
Fee: $0
________
Annual Notification
Notification Period: Prior notice required
Fee: $750
________
Emergency Notification
Notification Period: Prior notice required
Fee: Twice the regular fee
________
Alternate Asbestos Work Practices
Notification Period: 10 day notice
Fee: Twice the regular fee
________
Demolition with non-friable roofing
Notification Period: 10 day notice
Fee: Twice the regular fee
________
Exception for hazardous conditions
Notification Period: 10 day notice
Fee: Regular Fee